The Project consists of the following main components:
Construction of the WPPs and all the internal connections and roads
Construction and/or modernization of overhead transmission lines
Construction and/or modernization of electricity substations needed for interconnection to the National Power Grid (“NPG”)
Up to date, the project has reached the following milestiones:
Feasibility Study (2007) and Project Study (2008) received positive conclusions from the Central State Service “Ukrinvestexpertise”
Environmental Impact Assessment (incl. botany, ornithology, herpetology, geology) completed and approved by the State Committee for Ecological Evaluation (2007)
Letter of Approval of the Joint implementation (JI) Project under Kyoto Protocol was received (2007) and Option agreement for sale of Emission Reduction Units prepared
Interconnection contract with NEC “Ukrenergo” signed for interconnection to the backbone power grid.
NEC “Ukrenergo” issued technical requirements and approved technical tasks in compliance with the contract
Permissions and approvals received from local organizations (sanitary and epidemiologic inspection service, fire inspectorate, road service organizations etc.) and local government authorities (2007-2008)
Electricity Production License for electricity generation issued in 2008 by NERC
Membership with the Wholesale Electricity Market acquired in 2009
Construction Permit granted in 2010 (preliminary phase, Western site)
ABB and ELTEL Networks approved for EPC
3 rounds of WTG tender completed (2006, 2009, 2011)